Project No. 7442: Water Main Replacement on Pioneer Boulevard from 160th to 166th Street
The Norwalk Municipal Water System, which is one of three water providers in the City of Norwalk, is committed to delivering high quality water and reliable service. The City is focused on improving and expanding its existing water distribution system. The 2015 Water Master Plan recommended construction of a new water distribution main along Pioneer Blvd. between 166th St. and 160th St. as well as the replacement of existing water main pipes along several commercial and residential cross streets between Pioneer Blvd. and Clarkdale Ave.
The City will move forward with installing approximately 3,335 feet of new 12-inch pipeline, 3,610 feet of new 8-inch pipeline, and 11 new fire hydrants. After construction in Pioneer Blvd. is completed, the work will progress in the easterly direction towards Clarkdale Ave. The streets affected by this work will be 166th St., 165th St., Cedarvale St., 164th St., Chesterton St., 163rd St., 162nd St., 161st St., and Algardi St.
The pipeline project is anticipated to begin early Spring 2023 and will approximately take six months to complete. Construction will be phased in order to minimize the impact to City residents and businesses. Those affected by construction or delays will be notified in advance of work in their area.